Accurate construction cost estimates are critical for planning, budgeting, and decision-making at every stage of a project. Different types of estimates are used depending on how much information is available and how far the project has progressed.
Below are the 7 most common types of construction cost estimates, along with their typical accuracy ranges.
1. Preliminary (Order of Magnitude) Estimate
This estimate is prepared at the very early stage of a project when limited information is available.
Purpose:
- Initial feasibility analysis
- Early budgeting decisions
Basis:
- Historical data
- Cost per square foot or similar benchmarks
Accuracy Range:
- –30% to +50%
This estimate is useful for high-level planning but should not be used for final budgeting.
2. Conceptual Estimate
A conceptual estimate is developed once the basic project concept is defined.
Purpose:
- Comparing design options
- Budget approvals
Basis:
- Preliminary drawings
- Similar past projects
Accuracy Range:
- –20% to +30%
It provides better clarity than a preliminary estimate but still carries moderate risk.
3. Budget Estimate
This estimate is used when the project scope becomes clearer and design development has started.
Purpose:
- Setting a working project budget
- Securing financing
Basis:
- Schematic designs
- Quantity assumptions
Accuracy Range:
- –15% to +25%
Budget estimates are commonly used by owners to control project costs during design.
4. Schematic Design Estimate
Prepared during the schematic design phase, this estimate reflects a more defined layout and materials.
Purpose:
- Design cost control
- Refining project budget
Basis:
- Floor plans
- Major system selections
Accuracy Range:
- –10% to +20%
At this stage, many major cost drivers are identified.
5. Design Development Estimate
This estimate is created when design details, materials, and systems are mostly finalized.
Purpose:
- Confirming project affordability
- Preparing for construction documents
Basis:
- Detailed drawings
- Material specifications
Accuracy Range:
- –5% to +15%
It is a reliable estimate for final budget adjustments.
6. Construction Document (Definitive) Estimate
This is one of the most accurate estimates, prepared once complete construction drawings and specifications are available.
Purpose:
- Final cost planning
- Contractor bidding comparison
Basis:
- Detailed quantity takeoffs
- Final specifications
Accuracy Range:
- –3% to +10%
This estimate closely reflects the actual construction cost.
7. Bid (Tender) Estimate
The bid estimate is prepared by contractors when submitting final bids for the project.
Purpose:
- Contract pricing
- Final cost commitment
Basis:
- Construction documents
- Supplier and subcontractor quotes
Accuracy Range:
- –2% to +5%
This is the most accurate estimate, as it is based on real market pricing.
Conclusion
Each type of construction cost estimate serves a specific purpose at different stages of a project. As project details increase, the accuracy of estimates improves. Using the right estimate at the right time helps reduce financial risk, avoid cost overruns, and ensure successful project delivery.
If you want, I can also:
- Optimize this for SEO keywords
- Rewrite it in simpler language
- Convert it into a blog + landing page format
- Add tables or infographics text
Just tell me 👍
